Verify jobs are on track to be completed on time

Verify jobs are on track to be completed on time

1.Click the Open icon on the toolbar. The Select Form dialog box opens.
2. Type job operations in the Filter field.
3. Click the web.JobOperations list item.
4. Click the OK button. The Job Operations form opens.
5. Click the Filter in Place icon.
6. Click to select the Complete check box in the Operation section. 
7. Click to clear the Complete check box in the Operation section. This will give you all operations 
that are not complete.
8. Click the Status drop-down arrow in the Job section.
9. Click the Released list item.
10. Type <[Todays Date] in the Start Date field.
11. Click the Filter in Place icon.
12. Click the X on the Job Operations form.

    • Related Articles

    • Verify jobs are scheduled

      If your job orders are not showing as scheduled then you must rerun APS Planning 1. Click the Open icon on the toolbar. The Select Form dialog box opens. 2. Type job orders in the Filter field. 3. Click the web.JobOrders list item. 4. Click the OK ...
    • Identify past due jobs

      Part 1: Look for past due jobs 1. Click the Open icon on the toolbar. The Select Form dialog box opens. 2. Type job orders in the Filter field. 3. Click the web.JobOrders list item. 4. Click the OK button. The Job Orders form opens. 5. Click the ...
    • Configure time off groups

      1.Open the Time Off Group Parameters form. 2. Click New. 3. Type ST_[your initials]_Time in the Time Off Group ID field. 4. Type time off group for student in Description field. 5. Verify the following fields are populated in the first line in the ...
    • Factory Track- Shop Floor

      see attachment
    • Factory Track- Warehouse Mobility

      see attachment