1. Click the Open icon.
2. Type shop floor in the Filter field.
3. Click the Shop Floor Control Parameters list item.
4. Click the OK button. The Shop Floor Control Parameters form opens.
5. Click the Outside Process Management tab.
6. Verify the Enable Outside Process Management check box is selected.
7. Click the Poitem Xref Method drop-down arrow.
8. Click the One Line list item.
9. Verify Ordered is selected in the PO Status field.
10. Verify Oper End Date is selected in the Po Due Date Calculation field.
11. Click the Save icon.
17 Lesson 1: Managing outside processes
12. Click the X on the Shop Floor Control Parameters form