Update planning parameters

Update planning parameters

Part 1: Verify General parameter settings
1. Click the Open icon on the toolbar. The Select Form dialog box opens.
2. Type planning parameters in the Filter field.
3. Click the Planning Parameters list item.
4. Click the OK button. The Planning Parameters form opens.
5. Verify the value displayed in the PO In field is 0. 
24 Lesson 1: How APS works with procurement
6. Verify the value displayed in the PO Out field is 0. 
7. Verify the Check PO requisitions check box is cleared.
Part 2: Verify APS parameter settings
1. Click the APS tab.
2. Verify the For Planning check box is selected in the Use Expedited Lead Time section. 
3. Click the Purchased/Transferred Items drop-down arrow in the Planned Order Consolidation
section.
4. Click the Days Supply list item.
5. Click the Save icon if changes were made.
6. Click the X on the Planning Parameters form
    • Related Articles

    • View planning workbench and planning detail

      Part 1: View the workbench 1. Click the Open icon on the toolbar. The Select Form dialog box opens. 2. Type material planner in the Filter field. 3. Click the Material Planner Workbench list item. 4. Click the OK button. The Material Planner ...
    • Set forecast parameters

      Part 1: View Planning Parameters settings 1. Click the Open icon on the toolbar. The Select Form dialog box opens. 2. Type Planning Parameters in the Filter field. 3. Click the Planning Parameters list item. 4. Click the OK button. The Planning ...
    • Verify scheduling parameters

      1. Click the Open icon on the toolbar. The Select Form dialog box opens. 2. Type scheduling in the Filter field. 3. Click the Scheduling Parameters list item. 4. Click the OK button. The Scheduling Parameters (Filter in Place) form opens. 5. Click ...
    • Configure work center status parameters

      1. Open the Work Center Status Parameters form. 2. Select AS-500 from the Work Center drop-down list. 3. Verify 60 is in the Refresh Interval field. If not, type it. 4. Type 80 in the High Efficiency Level field. 5. Type 50 in the Medium Efficiency ...
    • Update job BOM

      Part 1: Update the Job BOM 1. Click the Open icon on the toolbar. The Select Form dialog box open. 2. Type job operations in the Filter field. 3. Click the Job Operations list item. 4. Click the OK button. The Job Operations (Filter in Place) form ...