APS Planning and Scheduling Messages
The errors listed in the table below appear on the APS Planning and Scheduling Messages form.
Error Message Explanation and Solution
ApsPlan: Error -30000 running the Planner. Network communications error. At some point in the planning or scheduling process, a network connection was lost. There are three possible causes:
The site parameters on the APS Sites and Alternative Management form are not set correctly. Make sure you specify the same APS Server Service Port with which you start the planner database.
Your planner service is not running. Use the Server Service Configuration utility, or the APS Sites and Alternative Management form, to start the service.
There is an operating system configuration, hardware, or network problem.
ApsPlan: Error -30001 running the Planner. Network communications setup error. The process was not able to connect to the Planning and Scheduling Service. Check the Windows Services application to make sure apssrvr.exe is running and that TCP/IP is configured correctly on this machine.
ApsPlan: Error -30002 running the Planner. Cannot resolve host address. The process was not able to connect to the host machine that is specified in the Planning and Scheduling Service configuration.
ApsPlan: Error -30003 running the Planner. Version mismatch. The server and client (or DLL) are not compatible software versions. Contact Technical Support.
ApsPlan: Error -30004 running the Planner. Registry access error. The process was not able to retrieve connection information from the machine's Windows registry. The machine's registry permissions might not be set up correctly, or some of the registry files may have been deleted.
ApsPlan: Error -30005 running the Planner. Error connecting to SQL database. The process was not able to connect to the SQL database specified in the Planning and Scheduling Service configuration. Make sure the SQL Server Service is running on the SQL Server and that the database exists and is specified correctly in the Planning and Scheduling Service configuration.
ApsPlan: Error -30006 running the Planner. Error in SQL query. There is an error in the system code or the database schema. Contact Technical Support.
ApsPlan: Error -30007 running the Planner. Alternative not found. The alternative "0", specified on the APS Sites and Alternative Management form, was not found in the SQL database. Reenter the alternative 0 record on the APS Sites and Alternative Management form.
ApsPlan: Error -30010 running the Planner. Cannot retrieve planner connection information for the specified alternative. The alternative 0 record, specified on the APS Sites and Alternative Management form, does not specify valid planner database connection information (port number, host name, etc.).
ApsPlan: Error -30011 running the Planner. Error connecting to Planner Database Server. The APS Server Service Host, specified on the APS Sites and Alternative Management form, was not found or was down.
ApsPlan: Error -30012 running the Planner. Planner API returned error. Check apserror.txt to find the specific Planner API call and its return code.
ApsPlan: Error -30013 running the Planner. Planner database reload in progress, API call aborted. Another client session may have been running the APS Planning activity or a Get ATP/CTP process. Wait a few minutes and try the task again.
ApsPlan: Error -30014 running the Planner. Planner database is marked as down. The planner database specified for the alternative 0 record, specified on the APS Sites and Alternative Management form, is not running. Verify that the database is running in the Server Service Configuration utility.
ApsPlan: Error -30016 running the Planner. Planner database reload was unsuccessful. See the ERRORLOG table for details. Check the ERRORLOG table in the SQL database. Find the detailed error message in the ERRMSG column. ERRORLOG messages are described below in the ERRORLOG Messages section.
ApsPlan: Error -30018 running the Planner. The Planner is currently running for the specified alternative. The APS Planning activity was running or another client session was accepting the Projected date during a Get ATP/CTP process. On the APS Sites and Alternative Management form, click Actions > Clear Planner Status.
ApsPlan: Error -30019 running the Planner. Generation of planned orders was unsuccessful. See ERRORLOG table for details. Check the ERRORLOG table in the SQL database. Find the detailed error message in the ERRMSG column. ERRORLOG messages are described below in the ERRORLOG Messages section.
ApsPlan: Error -30020 running the Planner. Flushing of the gateway table was unsuccessful. See ERRORLOG table for details. Check the ERRORLOG table in the SQL database. Find the detailed error message in the ERRMSG column. ERRORLOG messages are described below in the ERRORLOG Messages section.
ApsPlan: Error -30029 running the Planner. Flush of gateway table in progress, API call aborted. The APS Planning activity was running when the TaskMan service tried to run it. This error means that the system thinks a Planning function is already running, specifically the flushing of information between the SyteLine SQL database and the planner database. This situation can occur if the function had been interrupted for some reason and was unable to reset its status.
The solution is to reset the STATUSNO column to 0 (zero) in the ERDB table of the SyteLine SQL database.
ApsPlan: Error -30031 running the Planner. Cannot retrieve site connection information for one of the sites. The data in the APSSITE table for a site specified on the APS Sites and Alternative Management form is missing or invalid.
ApsPlan: Error -30032 running the Planner. Error connecting to APS Server. The APS Server Service Port number, specified on the APS Sites and Alternative Management form, is not valid. Check the Windows Services configuration to verify the port number on which the APS Server Service is running, and correct the entry.
ApsPlan: Error -30034 running the Planner. Planner database host or port does not match site information. The planner database host and/or port (in the APSSITE table) specified at the local site does not match what is defined at the remote site.
ApsPlan: Error -30035 running the Planner. Error starting global planner run. Check apserror.txt for more detailed error messages.
ApsPlan: Error -30036 running the Planner. Error ending global planner run. Check apserror.txt for more detailed error messages.
ApsPlan: Error -30037 running the Planner. ApsSchedulerStartSp returned an error. For more detailed error messages, check apserror.txt or run this query:
EXECUTE dbo.ApsSchedulerStartSp 0, -1
ApsPlan: Error -30038 running the Planner. ApsPlannerStartSp returned an error. For more detailed error messages, check apserror.txt or run this query:
EXECUTE dbo.ApsPlannerStartSp 0, 2, '*', -1
ApsPlan: Error -30039 running the Planner. Add alternative failed, API call aborted. Check apserror.txt for more detailed error messages.
ApsPlan: Error -30040 running the Planner. Alternative already exists. Specify a different alternative number.
ApsPlan: Error -30041 running the Planner. Alternative not a valid number, check value or license. Specify an alternative number between 1 and 999.
ApsPlan: Error -30043 running the Planner. A remote site definition is missing. Verify that all of your transfer items have a valid site specified.
Order record does not exist for scheduled operation at [%s] for order [%s] and resource [%s] The order listed in the SCHEDOP record does not exist in the ORDER table in the SyteLine SQL database. Contact Technical Support.
Unable to add shift [%s]
Unable to add calendar [%s]
Unable to add offshift [%s]
Unable to add overtime shift [%s]
Invalid value for shift.
The shift, shift exception, or holiday already exists ("calendar" in the error message refers to a Holiday definition in SyteLine).
Unable assign a priority to site [%s] The site priority list index is not valid.
Unable to assign BOM [%s] to finished material [%s] When trying to add a bill of material to an item. The item was not found in the database.
The bill of material was not found in the database.
The item-bill of material list index was not found in the database.
Recursive bills of material are not allowed. Make sure the item is not a component of itself, either directly or through a subcomponent.
Unable to assign component material [%s] to BOM [%s] When trying to add an item to a bill of material, the bill of material was not found in the database.
The item was not found in the database.
The bill of material-item list index is invalid.
Recursive bills of material are not allowed. Make sure this task does not make the item a component of itself, either directly or through a subcomponent.
Unable to assign date range [%s] through [%s] to calendar [%s]
Unable to assign date range [%s] through [%s] to offshift [%s]
Unable to assign date range [%s] through [%s] to overtime shift [%s]
Unable to assign timeslot [%s] to shift [%s]
When adding a range of dates to a shift, shift exception, or holiday, the shift ID to be changed was not found in the database.
The shift, holiday, or shift exception has an invalid time or duration.
Unable to assign jobstep [%s] to process plan [%s] When adding an operation to a routing, the routing was not found in the database.
The operation was not found in the database.
The routing-operation list index is invalid.
Unable to assign local material [%s] to remote site [%s] When adding a supply site definition to an item, the item was not found in the database.
The remote supply site's Site/Entities record was not found in the database.
The item-site list index is invalid.
Unable to assign local order [%s] to remote order [%s] When adding information about a parent demand to a planned demand transfer order at the supply site, the parent demand was not found in the database.
The planned demand transfer order does not exist.
Unable to assign outsourced material [%s] to order [%s] When adding a purchased item to the order, the order was not found in the database.
The purchased item was not found in the database.
The order-item list index is invalid.
Unable to assign process plan [%s] to material [%s] When adding a routing to an item, the item was not found in the database.
The routing was not found in the database.
The item-routing list index is invalid.
The routing is being used by another item.
Unable to assign remote order [%s] to local order [%s] When creating a cross-reference record between a planned demand transfer order and its parent demand order, the parent demand was not found in the database.
The planned demand transfer order does not exist.
The order-remoteorder list index is invalid.
Unable to assign resource [%s] to offshift [%s]
Unable to assign resource [%s] to overtime shift [%s]
When assigning a resource to a shift exception, the shift was not found in the database.
The resource was not found in the database.
The shift-resource list index is invalid.
Unable to assign resource [%s] to resource group [%s] When assigning a resource to a resource group, the resource group was not found in the database.
The resource was not found in the database.
The resource group-resource list index is invalid.
Unable to assign resource [%s] to shift [%s] When assigning a resource to a shift, the resource was not found in the database.
The shift was not found in the database.
The resource-shift list index is invalid.
Unable to assign resource group [%s] to jobstep [%s] When assigning a resource group to an operation, the operation was not found in the database.
The resource group was not found in the database.
The operation-resource group list index is invalid.
Unable to assign token [%s] to remote order [%s] in planner database's OrderDashPart table Invalid value for the local order ID (which is part of a cross-reference record to associate the original demand to the planned transfer demand order at the supply site).
Unable to create remote order [%s] for local order [%s] When creating the cross-reference between a planned demand transfer order and its parent demand order, the planned demand transfer order was not found in the database.
Unable to include material [%s] on material delivery order [%s]
Unable to include material [%s] on order [%s]
When adding an item to a demand (purchase order, job, etc.), the demand was not found in the database.
The item was not found in the database.
The demand-item list index is invalid.
Unable to transfer BOM [%s] When sending a bill of material to the ERDB, the bill of material already exists.
Unable to transfer configuration parameters to the planner database. A parameter on the APS Sites and Alternative Management form is invalid (these errors are unlikely to occur; contact Technical Support).
Unable to transfer effectivity [%s] When sending an effectivity record to the planner database, the effectivity already exists.
Unable to transfer jobstep [%s] When creating an operation, the operation ID already exists.
Unable to transfer material [%s] When sending an item to the planner database, the item ID already exists.
Unable to transfer material delivery order [%s]
Unable to transfer order [%s]
When sending a demand (such as a purchase order, job, etc.) to the planner database, the demand ID already exists.
Unable to transfer process plan [%s] When sending a routing to the planner, the routing ID already exists.
When sending demands to the planner database, the system is unable to send routings and BOMs. Search the product knowledge base at our support web site for the solution to this problem or contact Support.
Unable to transfer resource [%s] When sending a resource to the planner database, the resource ID already exists.
Unable to transfer resource group [%s] When sending a resource group to the planner database, the resource group ID already exists.
Unable to transfer site [%s] When sending a site record to the planner database, the site ID already exists.
WARNING: Routing not found, planning using lead time instead The item does not have a routing; the system planned it using the item's standard lead time.
BLOCKED: Unsatisfied resource combinations for operation The operation required more resources than are available from this resource group. The system planned the operation using all available resources from the group and continued planning.
BLOCKED: Line item 1 cannot be planned The item number refers to the sequencing of end item processing for Order Maximum groupings for the indicated order.